How to order engine parts earlier with demand forecasting (estimated ordering labour saving up to R$21,397 a year)
An improvement case in Aviation and Aerospace Component Manufacturing (Maintenance): total declared cost down 18%, saving $2,649 a year (savings from: Labor). Trust level: Unverified.
Current problem:
Celma is a high-volume shop serving several commercial engine lines, far from many US suppliers, so turnaround time per engine matters. When a part is missing, planners substitute or wait. That delays redelivery and limits throughput. One engine can need orders for hundreds of parts, each following its own flow.
Improvement mechanism:
Root causes first. Problem solving and daily visual management exposed where material flow stuck. The team then spent three months at the main LEAP shops in Lafayette (USA), Subang (Malaysia) and Celma, following engines from arrival to redelivery. Material planning showed the largest potential, balancing inventory against turnaround time. Data for forecasting. Operating data, engine configuration, past shop visits and predicted workscope were combined. The model estimates the probability of when parts will be needed, weighing around 300 parameters per incoming engine, for the single engine and across the fleet. Earlier orders. The tool, AI Materials Assistant (AIMA), also looks at current stock and places orders sooner for selected parts, so the fulfilment team gets signals before the engine is inducted. Standard process, connected systems. The model was paired with FLIGHT DECK (the company's lean system) to define standard processes, and an application linked to enterprise systems automates selected planning tasks. At Lafayette, inspection found worn turbine parts three and a half weeks into a visit. Such parts usually take about a month, risking up to six days of delay. The forecast meant they were already on the shelf. PUBLISHED CHANGES (without absolute before and after values) - On-time material orders up 24%. - Ordering within catalog lead time improved 25%. - On-time material delivery up 13%. - Ordering effort down by as much as 38 hours per month in some cases. MONEY VALUE (ESTIMATE) This is the poster's estimate using public Brazilian pay data, not a figure published by GE Aerospace. Ordering effort fell by as much as 38 hours a month, or up to 456 hours a year. Value = hours x cost of one labour hour. - Low: materials scheduler and controller average pay, R$19.92 an hour, no on-costs: up to R$9,084 a year. - Middle: same pay plus 68.18% labour on-costs: up to R$15,277 a year. - High: materials planning analyst average pay, R$27.90 an hour, plus 68.18% on-costs: up to R$21,397 a year. - Pay: national averages from CAGED records on Portal Salario, November 2026. Both job titles are proxies; actual pay at Celma is not published. - On-costs: Guia Trabalhista table for monthly-paid staff at companies outside the Simples tax regime, covering 13th salary, vacation and mandatory contributions. - Use your own figures: hours saved per month x 12 x labour hour cost. - Saved hours become money only if the person does other valuable work, or overtime or hiring falls. - Benefits from on-time delivery are not counted and the cost of building the tool is not deducted. Rate sources: - Materials scheduler and controller pay (Portal Salario) - Materials planning analyst pay (Portal Salario) - Labour on-cost table (Guia Trabalhista)
Solution:
GE Aerospace's overhaul shop in Celma, Brazil piloted an AI planning assistant on the LEAP engine line to forecast which parts will be needed and order them before engines arrive. On-time material orders rose 24% and on-time material delivery rose 13%. Poster's estimate of the ordering labour value: up to R$9,084 to R$21,397 a year.
Result:
Before the improvement, the cost items declared in this case ran at $1,249 per month.
After the improvement, those same items run at $1,028 per month.
The saving is $221 per month, or $2,649 per year - a 17.7% reduction measured against the cost of the items declared in this case (Labor), not against the full product cost.
The author has not declared any investment for this improvement.
The payback time cannot be worked out. Investment cost not provided yet - payback time cannot be calculated for comparison.
Lessons learned:
Study the process on site to find the real constraint before adding a model. Tie the tool to standard work and existing systems.
Reusable knowledge
Where this applies:
- Repair work with long-lead parts whose need is confirmed only after teardown. - Enough history on repairs, configurations, stock and lead times. - Planners who check and act on the forecast.
Risks:
- The cost table is the poster's estimate for one example position (one materials scheduler, a 215-hour paid month, entered as 27 days of 8 hours at 99.54% efficiency; salary R$4,283 plus 68.18% on-costs, equal to R$7,203.15), not GE Aerospace's cost. It takes the upper figure of 38 hours and matches the middle case. - Money figures are the poster's estimate, not published by GE Aerospace. It is unclear whether the 38 hours apply to one person or a team. - Pilot results published by GE Aerospace itself, with no independent check. - No baseline levels, order counts or measurement period for the percentages. - The 38 hours per month saving is the upper figure, in some cases, based on planner feedback. - Wrong forecasts raise inventory. No inventory or forecast accuracy figures are given. - No development cost and no new turnaround time.
Author's evidence:
Track on-time material orders, orders placed within catalog lead time, on-time delivery, monthly ordering hours and delay days caused by missing parts.
Reusable idea:
Forecast material from repair history and configuration, pre-order long-lead items, and measure on-time rates and delay days against inventory. How to start in your shop (added by the poster, works without AI): 1. Log every wait for material: part number, days waited, step where the shortage appeared. 2. Rank part numbers by total waiting days. 3. For the top ones, compare real lead time with the order date. 4. Check repair history: which equipment and conditions usually need that part. 5. Keep a pre-order list for repeating cases, with one approver. 6. Watch added inventory as well as saved waiting days. 7. Measure the same figures again and compare.