How to cut rework and work in process in a fan blade repair shop by re-laying out the floor (estimated labour saving up to HUF 25,022,651 a year for a 10-person team)
An improvement case in Aviation and Aerospace Component Manufacturing (Maintenance): total declared cost down 24%, saving $66,591 a year (savings from: Labor). Trust level: Unverified.
Current problem:
The site repairs fan blades for CFM LEAP, GEnx and GE90 engines. In early 2025, two autoclaves (ovens using heat and pressure to cure composites) needed rework, and production paused. By April work in process had nearly doubled. On the LEAP blade line, paint repair and polyurethane paste repair were flagged, the paste step causing rework daily. Painting and labeling sat with an outside supplier. In the 117,000-square-foot building, moving between stations could take hundreds or thousands of steps.
Improvement mechanism:
A focused kaizen. In May 2025 nearly 120 people joined a shingijutsu kaizen on LEAP fan blades and set yield and performance targets. Daily and visual management. Managers reviewed each repair step for causes of rework; operators pointed out safety and ergonomic issues, bottlenecks and waste. Painting brought inside. Keeping parts on site allowed one-piece flow. Painting was standardised, steps were combined and workstations added. Floor plan in work sequence. Related stations were placed next to each other. Better workplaces. A U-shaped preparation table, fewer trip hazards, new clamps and protective foam for safer blade handling. A steadier productivity measure. Mixed programmes made deliveries vary, so the site now tracks parts completed per operator per shift. PUBLISHED CHANGES (without absolute values) - LEAP blade cell transport time down 90%, in some cases from a few thousand meters of travel to a few hundred. - Total blade travel inside the plant down over 80%. - Cycle time down 32.4%. - Composite part rework down 62.5% over 12 months. - In-process inventory for those parts down more than 50%. - Backlog down 75%. - Parts per operator per shift up 31%. MONEY VALUE (ESTIMATE) This is the poster's estimate for an example team of 10 operators using public Hungarian pay data, not a figure published by GE Aerospace. Parts completed per operator per shift rose 31%, so the same workload needs about 23.66% fewer labour hours. Value = monthly pay x 10 people x 12 x 23.66%. - Low: regular gross earnings, business sector, HUF 703,100 per person a month, no on-costs: HUF 19,965,893 a year. - Middle: same pay plus 13% employer social contribution tax: HUF 22,561,459 a year. - High: national average gross earnings, HUF 779,800, plus 13%: HUF 25,022,651 a year. - National figures, not aerospace-specific; actual pay at the site is not published. - Use your own figures: monthly labour cost x (1 - 1 / (1 + productivity gain)) x 12. - Saved hours become money only if workload stays the same and freed people do other work, or overtime or hiring falls. - Gains from less rework and less work in process are not counted, and investment is not deducted. Rate sources: - KSH earnings release, March 2026 - PwC Hungary tax summary, employer social tax
Solution:
GE Aerospace's component repair site near Budapest had a pile-up after a temporary production stop. The team arranged stations in work order, brought final painting and labeling in-house and standardised tasks. Over 12 months composite rework fell 62.5% and in-process inventory for those parts fell by more than 50%. Poster's estimate for an example team of 10: HUF 19,965,893 to HUF 25,022,651 of labour a year.
Result:
Before the improvement, the cost items declared in this case ran at $23,450 per month.
After the improvement, those same items run at $17,901 per month.
The saving is $5,549 per month, or $66,591 per year - a 23.7% reduction measured against the cost of the items declared in this case (Labor), not against the full product cost.
The author has not declared any investment for this improvement.
The payback time cannot be worked out. Investment cost not provided yet - payback time cannot be calculated for comparison.
Lessons learned:
A forced restart is a chance to change layout and methods. Choose a productivity measure that order mix cannot distort.
Reusable knowledge
Where this applies:
- Multi-step repair or production where parts visit many stations. - Stations can be moved. - Bringing work in-house needs people, space and inspection capability.
Risks:
- The cost table is the poster's estimate for an example team of 10 (HUF 703,100 plus 13% = HUF 794,503 per person a month, 21 days of 8 hours; the same output needs 1/1.31 of the hours), not GE Aerospace's cost. It matches the middle case. - Money figures are the poster's estimate, not published by GE Aerospace. - Results are published by GE Aerospace itself, with no independent check. - The site had just paused production, so the starting backlog may have been unusually high. - Many actions ran together; their separate effects are unknown. - No investment, in-sourcing cost or money saved is published.
Author's evidence:
Measure cycle time, rework rate, work in process, backlog, transport time and distance, and parts per operator per shift.
Reusable idea:
Bring in a short outsourced step when it blocks one-piece flow, place stations in work order and measure parts per person per shift. How to start in your shop (added by the poster): 1. Pick a part family. Record lead time, reworked pieces and pieces in process. 2. Draw the layout and the real path of a part, and measure the distance. 3. List outsourced steps that interrupt flow, with waiting time out and back. 4. Rank rework causes by count and labour hours, and fix the top one. 5. Rearrange stations on paper in sequence and ask operators before moving. 6. Write standard work for changed steps. 7. Measure the same figures over the same period and compare.