Automotive component costing: machine build economics, inverted by volume
Costing a component or assembly for vehicles. The build-up matches machinery manufacturing, but high volume sinks the one-time costs and raises the cost of quality in their place.
The build-up matches machinery manufacturing: an assembly of made parts, bought parts and subcontracted parts. Read that guide first — the three-way split and the double-count trap when you supply material to a subcontractor both apply unchanged.
What differs is volume, and it reverses which categories matter.
One-time cost sinks, but does not disappear
Tooling, fixtures and design spread over program-lifetime volume, so the per-unit share becomes small. That tempts people to leave the field empty altogether, and that is the error.
Why it must be entered anyway: if the program ends earlier than planned, the unrecovered balance is a real loss. An entered figure can be recalculated; an empty field means nobody knows how much is still outstanding.
Cost of quality becomes a major category
At low volume, inspection is a few minutes of the operator's time. At high volume with very low defect targets, it becomes a block of its own:
- 100% or sampled inspection — labor, or gauge and machine time.
- Records and lot traceability — clerical time, plus retention cost.
- Retained samples and periodic destructive testing — product made that is never sold.
The third is the one most often missed, because it looks like ordinary production. It is product with no revenue, so it behaves like scrap — record it there, noting the cause is retained sampling rather than a defect.
Three changes from the machinery guide
| Category | What changes |
|---|---|
| Scrap | Add retained samples and periodic destructive tests, with the cause noted |
| Labor | Separate inspection and record-keeping time from production time |
| Tooling | Amortize over program-lifetime volume, not over one order |
The remaining seven follow the machinery guide.
Related guides
- Costing a machine build: roll up from parts, do not divide down from hours
A machine is an assembly of made parts, bought parts and subcontracted parts, each costed differently. How to roll them up, where the double count hides, and why commissioning is a cost line.
- NRE: design, fixtures and first build, and what you divide them by
At low volumes the one-time costs do not get thin. How to identify them, how to choose the quantity to spread them over, and why ignoring them makes a quote look competitive and lose money.
- Mold amortization and cavity economics: the arithmetic behind tooling decisions
More cavities means a more expensive tool and a cheaper part — up to a point. How to spread mold cost honestly, and how to compare two cavitation options with numbers instead of instinct.
What to do next
Now that you have read it, the fastest way to see your own numbers is to type them in. No account, nothing saved.
Run the numbers on your own figures →And if reading this made you realise you have already done it: leave it here, and the next person is spared the road you already walked.
Publish a case →